The last open phase of Deephaven's 2026 Street Improvement Project is scheduled to get its first lift of asphalt this week, with the final surface expected the week after. That puts the city on track for the end-of-October finish it promised in its third-quarter newsletter. The same issue called this the largest road project in the city's history.
This summer was the first stage of a longer job. The city is still working through miles of failing road, and three utilities are working on their own schedules. At least two of those schedules run into 2027. Here is where everything stands as of the city's Oct. 9 update. What happens next mostly depends on which street you live on.
Phase 3 is the last stretch, and it's running late
The road program started June 8. It covers about five miles of roadway, built in four smaller phases. According to the city's project page, Phases 1, 2 and 4 are functionally complete and down to punch-list work. Phase 3 is still active.
The original calendar was tighter. The Deephaven Digest estimated Phase 3 would run from August 31 to October 9, and it called those dates projections that would shift with weather and progress. By October 9, the weekly letter said concrete curbing and storm sewer installation were wrapping up that week. Astech, the contractor, was getting ready to shape and fine-grade the gravel base.
Here is the order of work left on Phase 3 streets, based on the October 9 update and the city's restoration notes:
- Fine grading of the gravel base to final elevation, the week of October 12.
- First lift of asphalt, planned for the same week.
- Topsoil behind the curb and in disturbed areas, starting after the first lift.
- Final asphalt surface, expected the following week.
- Seed or sod, which the city schedules after the final pavement layer.
The turf comes last, and that's the part to watch. The city says turf restoration follows the final pavement, but none of the published materials give a date for it. With the final surface pushed toward late October, any yard waiting on grass is waiting on the weather too. The contractor is responsible for restoring disturbed yards and repairing irrigation systems.
The method also explains why your street looked the way it did all summer. Deephaven used full-depth reclamation, which grinds the existing pavement and base in place into a stronger subgrade and then puts a new surface on top. The city's rule of thumb was that each phase would take six weeks or less, from pavement removal to final restoration. Residents should lose driveway access for about five days while new concrete curb cures.
Cottagewood Road gets dug up one more time
City crews didn't cause most of this summer's closures. The Digest said plainly that CenterPoint Energy's gas main replacement would have the larger impact. CenterPoint's plan called for full road closures at different times on Minnetonka Boulevard, Vine Hill Road and Cottagewood Road.
CenterPoint's project page lays out how the work moved through town:
| CenterPoint phase | Work area | Estimated timing |
|---|---|---|
| Phase 1 | Minnetonka Blvd, Carsonwood Ave to the Lake Minnetonka Regional Trail | One week from June 15 |
| Phase 2 | Minnetonka Blvd to Cottagewood Rd, extending west on Cottagewood to Maple Hill Dr in early July | June 22 to around July 20 |
| Phase 3 | Carsonwood Ave to Minnetonka Blvd, with Circle Dr closed at Minnetonka Blvd | About July 20 to August 28 |
| Phase 4 | Cottagewood Rd west of Vine Hill Rd | Until fall 2026 |
Phase 4 is the one still open. On October 9, the city reported that CenterPoint had finished installing gas main in its final phase and was pressure testing so the new mains could go into service. Restoration on Cottagewood Road was expected to begin the following week. The Digest's projected fall closure window ran from September 1 to October 24. So for anyone west of Vine Hill Road, one more round of surface work is coming even as the city's own phases close out.
One road on the gas list is a year away. CenterPoint says it will upgrade gas infrastructure along Northome Rd in 2027, a job it expects to take about three weeks, with restoration after.
The piece of this summer you won't drive on
The longest-lasting project of the season is in a church parking lot. Phase 2 includes a stormwater infiltration basin in the lower lot of Calvary Lutheran Church, built for the Montgomerie Avenue Stormwater Improvement Project. The plan removes the eastern part of the lot and shifts the remaining parking north to make room.
Here is the problem it's meant to solve. The city says runoff from about 5.6 acres of nearby streets and properties collects in a low spot on Montgomerie Avenue. From there it runs across several private properties into the storm sewer and on to Lake Louise. The city describes the basin as capturing and infiltrating storms up to one inch, which covers about 90% of rainfall events in the area. City figures put the reduction at nearly six pounds of phosphorus a year, and the basin is expected to remove more than 1,000 pounds of suspended sediment each year before the water reaches Lake Louise and Robinson's Bay. The Minnehaha Creek Watershed District provided technical and financial support through its Land and Water Partnership Program. The DNR and the Minnesota Board of Water and Soil Resources added grant funding.
Storm sewer pipes in poor condition were replaced inside several phases, and the Thorpe Park parking lot was repaved in Phase 1.
What's already scheduled for 2027 and beyond
The bigger number comes from the city's own survey. The 2024 Road Ratings Survey listed nine miles of Deephaven roadway in poor or failing condition. This year's project and the associated work cover six of those miles. The other three are set to be repaired "in the next three to five years." The city hasn't published which streets are next. Every road crew leaving town this fall is leaving a street list that is only two-thirds done.
The utilities have their own schedules, run by the companies themselves rather than the city:
- Midco fiber. Midco is building a fiber network across Deephaven in phases. Its goal is to make service available to all residents by the end of 2026. The main lines go in mostly by directional drilling, with spot excavation for connections. The buildout covers the main network only, so a home gets connected when the homeowner arranges installation with Midco. Midco's Deephaven page has a map that sorts areas into future, active, awaiting activation and available.
- Xcel Energy. Xcel plans to replace the poles and wires on an overhead line that runs from Shorewood through part of Deephaven. The rebuild is set for 2027, with tree clearing and prep work this fall. The city's spring newsletter showed the route on a map. It also said pole installation was unlikely before 2027 and that brush clearing would run through spring, summer and fall 2026.
- Met Council lift station L48. The restoration work includes extra paving, driveway patching and touch-ups, plus new turf on Cottagewood Road and parts of Ridgewood Road and Vine Hill Road. Updates are posted on the Met Council project page.
The city lists a contact for each one on its project page. For questions about the road project itself, the onsite construction manager is Nick Olson at (952) 262-6163.
October 31 on Cottagewood Road
The street work and the neighborhood's own season happen to end in the same stretch of weeks. When the Digest announced the October finish, it added, "If you were looking for reasons to have a Halloween party, completion of the road work projects around town can be added to your list."
The Cottagewood General Store at 20280 Cottagewood Avenue already has one on the calendar. Its Halloween / Closing Day is Saturday, October 31, from 4 to 7 p.m. It's the last day of the season, with candy and costumes before the store closes for the year. The store opened its 2026 season on May 2, so it ran for the whole construction summer. The nonprofit Cottagewood Community Foundation owns and runs it.
Winter at the parks comes next. The city lists ice rinks and warming houses at Thorpe Park, 3725 Hamilton Ave., and at Village Hall Park, 20225 Cottagewood Road, with opening dates to be posted as the season gets closer. The city's Winter 2026 newsletter said the 2026 capital budget would pay for building a warming house at Village Hall Park. Hours for this winter haven't been announced. Last winter's posted hours were 1 to 9 p.m. Monday through Saturday and noon to 9 p.m. on Sundays and holidays, weather permitting.
Owners on a Phase 3 street, or on the stretch of Cottagewood Road still being restored, may have a sale or a valuation coming up. Unfinished turf and a new, smooth road surface show up differently in listing photos and in a buyer's first walk-through. The Petersen Team tracks these local projects street by street. If you're thinking about next spring, we can walk you through how this season's work fits into your home's value. Request a home valuation, and we'll start with your street.